Ivory
Building new - February 2026
The ceiling above the fifth floor has been poured. Work has begun on preparing and pouring the structural elements of the sixth floor.


+9
More photos
Building new - January 2026
We are continuing our work on the third floor.


+2
More photos
Building new - January 2026
The ceiling above the third floor has been poured. Work has begun on preparing and pouring the structural elements of the fourth floor.


+5
More photos
Building new - December 2025
The ceiling above the second floor has been poured. Work has begun on preparing and pouring the structural elements of the third floor.


+2
More photos
Building new - November 2025
The ceiling above the first floor has been poured. Work has begun on preparing and pouring the structural elements of the second floor.


+13
More photos
Building new - October 2025
Earthworks. Underground construction of the building.
Building new - October 2025
Earthworks. Underground construction of the building.


+4
More photos
Building new - August 2025
Earthworks. Underground construction of the building.



+3
More photos

Building new - August 2025
Earthworks. Underground construction of the building.



+7
More photos

Building new - May 2025
Earthworks. Underground construction of the building.